I've got a few new photos of this development, so I thought I'd just put all the shots from the same angle together to show how it's been coming along.


Jan. 30


Feb. 3


Feb. 15



Feb. 18


April 4


April 21


April 29


May 5


May 10


May 25


June 10


June 30


July 9


July 15


July 21


July 30


Aug. 8


Aug. 15


Aug. 31


Sept. 9



Sept. 22


Oct. 6


Oct. 12


Oct. 23


Nov. 8

The pace really began picking up in July, and now it's rising one floor per week. [Update, Sept. 20] As it's set to have 12 floors, it should be done in 3-4 weeks. [It was finished Oct 31].

1 comment:

Jon Allen said...

wow, they are moving quickly.

At the IFC Seoul construction site, they are still going deeper on the excavations.